Wednesday 29 June 2011

Slab and Frame Stage

So Renee took a drive on Friday to see if the concrete was being poured, well she was 24hrs too late as it had been done a day ahead of schedule and had been laid on Thursday!  Luckily the weather was great all weekend so gave it time to set before framing started on Monday.  James took a drive to see what had gone up and nearly the first floor has been finished! He spoke with the framers on site and they said that the upstairs should be complete by the end of the week.  If they keep it up we'll be in in a few weeks (OK a slight exaggeration, but feels like it!).

Friday 24 June 2011

So what are we actually building?

So after wandering around a number of houses we decided on the Newington 40sq from Carlisle Homes.  It met all our requirements and we loved the layout. 

Friday 10 June 2011

Site start!

Today worked started on the site :) Slab pour is currently scheduled for 24th June. It's all go now!