We received the lock up stage claim on Friday, so from site start to lock up we're at 10 weeks and from slab pour to lock up is just 8 weeks. Before we got locked out, I managed to grab a few photos of the interior.
Stairs!
Balusters should be Stainless Steel, although the black could just be protecting the underlying finish. Something to check with the SS on Friday.
Ensuite units
Kitchen - The island should be the same colour as the top cabinets - raised this with our CLE and it's being resolved.
Bathroom unit
Weatherboards on the back